OBJECTIVE
The replacement of an existing HF Storage Tank. Special consideration was given to the handling of contaminated equipment and materials.
HIGHLIGHTS
The highlights of this project included the re-routing of several HF and MIBK pipe lines which allowed for the removal of the existing HF storage tank. Once the new tank was in position, a new structural platform was installed to provide access to the valving and instrumentation on the top of the tank.
The project also included electrical tie-ins for new instrumentation, along with an update to the electrical area classification documents.